Construction Update

Goran has completed the grading, prepping and paving of Beartooth Lane. They have also completed work on the storm drain pipe south of Robinson along the shoulder of Broadway. Additionally, they are working on the open channel ditch east of Beartooth Lane. The north bound lane of Broadway is temporarily closed at the intersection with Beartooth while Goran paves the approach. Flaggers are present to keep traffic flowing in a "one-way" pattern. Traffic will be detoured from 3rd to Robinson starting the week of June 2.